Wednesday, January 25, 2012

DRB Approves Aqua, VA Cooling Tower Proposal

Drawing submitted by Aqua, VA of the proposed cooling tower installation as seen from  the tennis courts.
At last night's DRB meeting, the DRB voted to approve the addition of the cooling tower structure proposed by Aqua, VA to be added to the current RELAC facility. The cooling towers are intended to increase the efficiency of the operation and eliminate the need for the diesel generator at times of low lake water levels. The proposal includes sound proofing/noise reduction features designed to keep any additional plant noise levels down.

Aqua, VA will now have to decide whether to green light the project. If they do, they will start the permit process and then hope to start construction in the Spring with the goal of being operational before a diesel generator becomes necessary this coming season.

DOCUMENTS
Aqua Letter
Application
More Drawings

Tuesday, January 17, 2012

Tuesday 1/24/24: RELAC Cooling Towers to Be Proposed to DRB

AQUA, VA (RELAC's owner) has sent the Design Review Board (DRB) at RA a packet with a proposal to DRB for installing two water evaporators (cooling towers). Proposal to be presented at the DRB meeting on Tuesday, Jan. 24th Meeting starts at RA Headquarters @ 7PM (Aqua is Item #6 on the DRB agenda).

Hickory Cluster president, Fred Swartzendruber, spoke with the engineer at AQUA who prepared the proposal and he has agreed to send PDF copies of the documentation (including before and after renderings and acoustic data) due to the short notice timing, docs below.  

DOCUMENTS
Application
More Drawings

Wednesday, June 3, 2009

RELAC: Plant Improvement Needed

RELAC cluster presidents and residents met on 6/2. Our Aqua Virginia representative was not able to attend but sent this letter. The proposed and necessary new pump station for the intake would cost $175,000 and the average user (average being $770/yr) an additional $160.00 per season.

Thursday, May 14, 2009

2009 A/C Season Is On

I wanted you all to know that we have the AC system operational – I assume we will have the usual period where we will need to deal with air in our and the customers’ lines. We began circulating water yesterday and have removed much of the air and are continuing today.
Thank You,
Greg

Gregory Odell
Chief Operating Officer
Aqua Virginia, Inc.